If you want to power off the healthy servers in the cluster, you must first shut down the cluster to avoid data loss.
To shut down a cluster:
The operation of the program's main components will be stopped. You can now power off the cluster servers.
To start up the cluster servers:
The cluster servers will start up.
The scaling management web interface becomes available when more than half of the cluster servers are started. For example, if there are 7 servers in the cluster, the web interface will be available when 4 servers of the cluster are powered on.