You can specify the cost of an individual link. All links built within the SD-WAN network are displayed in the overall table of links in the Tunnels section, as well as in the graphic topology in the Topology section. A table of links built using a particular CPE device is also displayed in the configuration of that CPE device, on the Tunnels tab.
To indicate the cost of the link, use the following instructions:
To specify the cost of a link using the overall link table:
In the menu, go to the Infrastructure section.
The SD-WAN infrastructure management page is displayed. By default, the Network resources tab is selected, which displays the table of SD-WAN Controllers.
Click Management next to the SD-WAN Controller and in the drop-down list, select Configuration menu.
This opens the SD-WAN Controller configuration menu. By default, you are taken to the Controller nodes section, which displays a table of Controller nodes.
Go to the Tunnels section.
A table of links is displayed.
Click Management next to the link and in the drop-down list, select Set cost.
This opens a window; in that window, select the Override check box to specify the cost of the link.
In the Tunnel cost field, enter the cost of the link.
To automatically assign the specified cost to the corresponding link in the opposite direction, select the Save for both tunnels check box.
To specify the cost of a link using the graphical topology:
In the menu, go to the Infrastructure section.
The SD-WAN infrastructure management page is displayed. By default, the Network resources tab is selected, which displays the table of SD-WAN Controllers.
Click Management next to the SD-WAN Controller and in the drop-down list, select Configuration menu.
This opens the SD-WAN Controller configuration menu. By default, you are taken to the Controller nodes section, which displays a table of Controller nodes.
Go to the Topology section.
The SD-WAN topology is displayed.
Click the link to open a window and in that window, click Set cost.
This opens a window; in that window, select the Override check box to specify the cost of the link.
In the Tunnel cost field, enter the cost of the link.
To automatically assign the specified cost to the corresponding link in the opposite direction, select the Save for both tunnels check box.